Dec. 23, 2009

Portneuf Medical Center Celebrates Steel Topping Out

The Portneuf Medical Center project celebrated a construction milestone--the final piece of steel being hoisted into place on the building's frame and the facility reaching its maximum height--with a steel topping out ceremony on Dec. 16, 2009. Layton is completing a six-story addition and multiple renovations to the 350,000-square-foot hospital to consolidate Portneuf's east and west campuses.

Layton currently has 200 workers on site performing everything from site work to overhead rough-in. Because of their hard work the project has noted several milestones:

  • 5,843 tons of demolition has been completed
  • 27, 332 cubic yards of earth has been moved
  • 11,300 cubic yards of concrete has been placed
  • 2,800 tons of steel has been erected
  • miles of pipe and conduit have been installed

The project is currently two weeks ahead of schedule and is on track to be complete in June 2011.

# # #

 


Other Layton News

 

 

Media Contact:
Alan Rindlisbacher
Marketing Director

(801) 563-3722

Layton Blog :
http://blog.laytoncompanies.com

Media Resources:

Layton Logos
Photographs
Request Specific Resources

Layton Publications:

Copyright 2010 The Layton Companies